Actuarial Notes

Estimating Unpaid Claims Using Basic Techniques

By Jacqueline Friedland · Casualty Actuarial Society · 2010

Study guide: Exam 5

A CAS text on estimating unpaid claims for property and casualty insurers, reinsurers and self-insured entities using basic techniques. Written by Jacqueline Friedland of KPMG, with significant contributions by Rachel Dutil and Edward Lam, it was created to replace a number of readings on the CAS's 2007 syllabus with a single educational publication. Its four parts are Introduction, Information Gathering, Basic Techniques for Estimating Unpaid Claims, and Estimating Unpaid Claim Adjustment Expenses; three appendices reproduce a CAS statement of principles and two actuarial standards of practice. This is Version 3, dated July 30, 2010, which added Chapter 17.

On the syllabus

  • Exam 5 — objectives B1–B20; all chapters (the Appendices are excluded), in the Third Version of July 2010.

Part 1 Introduction

1 Overview

  • Importance of Accurately Estimating Unpaid Claims
    • The importance of accurate estimates of unpaid claims is seen from three viewpoints: internal management, investors and regulators.
  • Further Requirements for Accurate Reserves
  • Organization of This Book
  • Ranges of Unpaid Claim Estimates
    • The book focuses on point estimates; addressing ranges of unpaid claim estimates is beyond its scope.
  • Background Regarding the Examples
  • Key Terminology
    • The unpaid claim estimate has five components — case outstanding on known claims, provision for future development on known claims, estimate for reopened claims, provision for claims incurred but not reported, and provision for claims in transit — and the last four together are the broad definition of IBNR.
    • IBNR is often separated into pure IBNR (incurred but not yet reported) and IBNER (incurred but not enough reported, or development on known claims).

2 The Claims Process

  • Overview
    • Claims professionals estimate case outstanding on reported claims; actuaries are responsible for estimating the remaining components of total unpaid claims.
  • Claims Professionals
  • A Claim is Reported
  • The Life of a Claim
  • Further Claim Examples

Part 2 Information Gathering

  • Introduction to Part 2 – Information Gathering
    • Wiser's four phases — exploring the data, applying estimation techniques, evaluating the conflicting results, and monitoring projections over later calendar periods; Chapters 3 to 6 address the first.

3 Understanding the Types of Data Used in the Estimation of Unpaid Claims

  • Sources of Data
  • Homogeneity and Credibility of Data
    • The goal is to divide the data into sufficiently homogeneous groupings without compromising its credibility, the predictive value given to a group of data.
  • Types of Data Used by Actuaries
  • Organizing the Data

4 Meeting with Management

  • Understanding the Environment
    • Reporting and payment patterns, frequency and severity can be altered by changes in classes of business or geographical focus, policy provisions, reinsurance arrangements, claims management philosophy, claims processing lags, the legal and social environment, and the economic environment.
  • Sample Questions for Department Executives
    • Questions for a claims executive, an underwriting executive, a data processing or accounting executive, actuaries specializing in ratemaking, in-house actuaries, those managing reinsurance, and senior management.
  • Additional Questions

5 The Development Triangle

  • A development triangle is a table that shows changes in the value of various cohorts over time.
  • Rows, Diagonals, and Columns
  • Alternative Format of Development Triangles
  • Detailed Example of Claim Development Triangles
  • Other Types of Development Triangles
  • Naming Convention for Examples

6 The Development Triangle as a Diagnostic Tool

  • Development triangles are used to see how changes in an insurer's operations and in the external environment — such as in claims settlement and in the adequacy of case outstanding — influence the claims data.
  • Detailed Example – Background Information
  • Premium History
  • The Reported and Paid Claim Triangles
  • The Ratio of Paid-to-Reported Claims
  • The Ratio of Paid Claims to On-Level Earned Premium
  • Claim Count Triangles
  • Ratio of Closed-to-Reported Claim Counts
  • Average Claims
  • Summary Comments for XYZ Insurer
  • Conclusions

Part 3 Basic Techniques for Estimating Unpaid Claims

  • Introduction to Part 3 – Basic Techniques for Estimating Unpaid Claims
    • The Components of Ultimate Claims
    • Actuarial Judgment

7 Development Technique

  • The development technique, also known as the chain ladder technique, assumes that claims recorded to date will continue to develop in a similar manner in the future.
  • Key Assumptions
  • Common Uses of the Development Technique
  • Mechanics of the Development Technique
  • Unpaid Claim Estimate Based on the Development Technique
  • Reporting and Payment Patterns
  • Observations and Common Relationships
  • When the Development Technique Works and When it Does Not
  • XYZ Insurer
  • Influence of a Changing Environment on the Claim Development Technique

8 Expected Claims Technique

  • The expected claims technique assumes the actuary can better estimate total unpaid claims from an a priori estimate than from the claims experience observed to date.
  • Key Assumption
  • Common Uses of the Expected Claims Method
  • Mechanics of the Expected Claims Technique
  • XYZ Insurer
  • When the Expected Claims Technique Works and When it Does Not
  • Influence of a Changing Environment on the Expected Claims Technique

9 Bornhuetter-Ferguson Technique

  • The Bornhuetter-Ferguson technique splits ultimate claims into actual reported (or paid) claims and expected unreported (or unpaid) claims; as a credibility weighting of the development and expected claims methods, Z = 1.00 / cumulative development factor.
  • Key Assumptions
  • Common Uses of the Bornhuetter-Ferguson Technique
  • Mechanics of the Bornhuetter-Ferguson Technique
  • Unpaid Claim Estimate Based on Bornhuetter-Ferguson Technique
  • When the Bornhuetter-Ferguson Technique Works and When it Does Not
  • The Bornhuetter-Ferguson Method and Cumulative CDFs Less than 1.00
  • XYZ Insurer
  • Influence of a Changing Environment on the Bornhuetter-Ferguson Method
  • Benktander Technique
    • The Benktander method is a credibility-weighted average of the Bornhuetter-Ferguson technique and the development technique.

10 Cape Cod Technique

  • The Cape Cod (Stanard-Buhlmann) method obtains the expected claim ratio from the reported claims experience, with "used-up premium" as its denominator, instead of an independent, often judgmental selection.
  • Key Assumptions
  • Common Uses of the Cape Cod Technique
  • Mechanics of the Cape Cod Technique
  • Unpaid Claim Estimate Based on Cape Cod Technique
  • When the Cape Cod Technique Works and When it Does Not
  • XYZ Insurer
  • Influence of a Changing Environment on the Cape Cod Method

11 Frequency-Severity Techniques

  • In their simplest form, frequency-severity techniques multiply the estimated ultimate number of claims by the estimated ultimate average value.
  • Common Uses of Frequency-Severity Techniques
  • Types of Frequency-Severity Techniques
  • Frequency-Severity Approach #1 – Development Technique with Claim Counts and Severities
  • Frequency-Severity Approach #2 – Incorporation of Exposures and Inflation into the Methodology
  • Frequency-Severity Approach #3 – Disposal Rate Technique
  • When the Frequency-Severity Techniques Work and When they Do Not
  • Enhancements for Frequency-Severity Techniques
  • Frequency-Severity Projection as Input to Bornhuetter-Ferguson Technique

12 Case Outstanding Development Technique

  • The case outstanding development technique assumes that claims activity related to IBNR is related consistently to claims already reported, so it suits lines whose claims are mostly reported in the first accident period — which makes it strong for claims-made coverages and report year analysis.
  • Case Outstanding Development Technique – Approach #1
  • Case Outstanding Development Technique – Approach #2

13 Berquist-Sherman Techniques

  • Reacting to a Changing Environment through Data Selection and Rearrangement
  • Treat Problem Areas through Data Adjustment
    • Detecting Changes in the Adequacy Level of Case Outstanding and Reducing the Effect of Such Changes on Reported Claims Projections
    • Detecting Changes in the Rate of Settlement of Claims and Adjusting Paid Claims for Such Changes
    • The Berquist-Sherman adjustments restate the case outstanding triangle for changes in case outstanding adequacy, and the paid claim triangle for changes in the rate of claims settlement, before development techniques are applied.
  • XYZ Insurer

14 Recoveries: Salvage and Subrogation and Reinsurance

  • Salvage, Subrogation, and Collateral Sources
  • Estimating S&S Recoveries – Auto Physical Damage Insurer
    • Salvage and Subrogation recoveries are projected with the development technique on reported and received S&S, and with a ratio approach developing the ratio of received S&S to paid claims.
  • Reinsurance and Aggregate Limits

15 Evaluation of Techniques

  • Actuaries should use more than one method when analyzing unpaid claims; no single method can produce the best estimate in all situations.
  • U.S. Industry Auto
  • XYZ Insurer
  • Changing Conditions – Changes in Claim Ratios and Case Outstanding Adequacy and Changes in Product Mix
  • Berq-Sher Insurers
  • Monitoring and Interim Techniques for Unpaid Claim Estimates

Part 4 Estimating Unpaid Claim Adjustment Expenses

  • Introduction to Part 4 – Estimating Unpaid Claim Adjustment Expenses
    • Actuaries in Canada still separate ALAE and ULAE; for U.S. Schedule P reporting the NAIC introduced defense and cost containment (DCC) and adjusting and other (A&O) expenses, effective January 1, 1998.

16 Estimating Unpaid Allocated Claim Adjustment Expenses

  • All the development techniques of Part 3 can be used with ALAE; the greatest challenge is often obtaining ALAE data separate from claim-only data.
  • Example – Auto Property Damage Insurer
    • Reported and paid ALAE development, the development of the ratio of paid ALAE to paid claims, and that ratio with additive rather than multiplicative development factors.
  • Choosing a Technique for Estimating Unpaid ALAE

17 Estimating Unpaid Unallocated Claim Adjustment Expenses

  • The two broad classifications of techniques for ULAE are dollar-based and count-based; the chapter relies extensively on Conger and Nolibos (2003), "Estimating ULAE Liabilities: Rediscovering and Expanding Kittel's Approach".
  • Dollar-Based Techniques
    • Classical (or Traditional) Technique
    • Kittel Refinement
    • Conger and Nolibos Method – Generalized Kittel Approach
    • Mango-Allen Refinement
  • Count-Based Techniques
    • Early Count Techniques
    • Wendy Johnson Technique
    • Mango-Allen Claim Staffing Technique
    • Rahardjo
    • Spalla
  • Triangle-Based Techniques
  • Comparison Example

Appendices – Statement of Principles and Actuarial Standards of Practice

Appendix A Statement of Principles Regarding Property and Casualty Loss and Loss Adjustment Expense Reserves

Appendix B Actuarial Standard of Practice No. 43 Property/Casualty Unpaid Claim Estimates

Appendix C Actuarial Standard of Practice No. 9 Documentation and Disclosure in Property and Casualty Insurance Ratemaking, Loss Reserving, and Valuations

List of Changes Implemented

  • July 30, 2010: Chapter 17 added, and the page number for Chapter 11 corrected in the table of contents.
  • July 22, 2009: hyperlinks and bookmarks added, "affect" changed to "effect" where appropriate, and corrections to exhibits in Chapters 13, 14 and 15.

Errata

  • Chapter 17, page 388, under "Challenges of the Classical Technique": the 25% and 75% ratios apply to opening and closing claims, implying 75% of the ULAE ratio applied to case outstanding and 100% to IBNR.

Related readings

  • ASOP 43 - Property Casualty Unpaid Claim Estimates (ASB - 2007) — reproduced in full as Appendix B, and cited in Chapter 1 for its definition of the actuarial central estimate

Sources