SOA Exam FM Sample Question 391

Study guide: Exam FM-2

A company is considering a project where it expects to pay and receive the following cash flows:

End of year Cash flow
2 Receives X
4 Pays Y
6 Receives X

When calculated using an annual effective rate of i (i > 0), the present value of this project is equal to 0.

Determine i.

  • A) \dfrac{Y \pm \sqrt{Y^{2} - 4X^{2}}}{2X}
  • B) \dfrac{Y \pm \sqrt{Y^{2} - 4X^{2}}}{2X} - 1
  • C) \sqrt{\dfrac{-Y \pm \sqrt{Y^{2} - 4X^{2}}}{2X}} - 1
  • D) \sqrt{\dfrac{2X}{-Y \pm \sqrt{Y^{2} - 4X^{2}}}} - 1
  • E) \sqrt{\dfrac{2X}{Y \pm \sqrt{Y^{2} - 4X^{2}}}} - 1